Schedule Estimating Threshold

Schedule Estimating Threshold When you create a schedule you generally don’t know enough to enter all of the detailed activities the first time though. Instead, you identify large chunks of work first, and then break the larger chunks into smaller pieces. These smaller pieces are, in turn, broken down into still smaller and more discrete activities. This technique is referred to as creating a Work Breakdown Structure (WBS). A question people ask is how small the activities should be before they do not need to be broken down further. This is referred to as your “estimating threshold”. Work can be broken down into smaller activities than the estimating threshold, but normally no work would be left at a higher level. The threshold can be different based on the size of your project and how well the work is understood. You can use the following criteria as a guide. For a typical large project (say 5000 effort hours or more) the activities should be no longer than two weeks. Medium and smal