Use the Schedule for Project Integration
In the TenStep ® Project Management Process, once the project is executing, all of the project management processes are integrated in the schedule. The integration occurs here because of an overriding philosophy of the TenStep process – “what’s in the schedule gets done”. In other words, all of the work of the project should be in the schedule and if an activity is not in the schedule, it should not be worked on. The schedule is the focal point of managing the project, and all the project management processes are integrated in the schedule. You should have activities and time allocated in your schedule for communicating, managing scope, updating the schedule and all other project management activities. The integration occurs when the project management processes touch each other, as well as when the project management and project lifecycle activities overlap. Consider the following examples: A large scope change request is approved, resulting in more work. This is a typical integrati...